Tasks Scheduling Order (medium)
Problem Statement
There are ‘N’ tasks, labeled from ‘0’ to ‘N-1’. Each task can have some prerequisite tasks which need to be completed before it can be scheduled.
Given the number of tasks and a list of prerequisite pairs, write a method to find the ordering of tasks we should pick to finish all tasks.
Examples
Example 1:
Input: Tasks=6, Prerequisites=[2, 5], [0, 5], [0, 4], [1, 4], [3, 2], [1, 3]
Output: [0 1 4 3 2 5]
Explanation: A possible scheduling of tasks is: [0 1 4 3 2 5]
Example 2:
Input: Tasks=3, Prerequisites=[0, 1], [1, 2]
Output: [0, 1, 2]
Explanation: To execute task '1', task '0' needs to finish first. Similarly, task '1' needs to finish before '2' can be scheduled. A possible scheduling of tasks is: [0, 1, 2]
Example 3:
Input: Tasks=3, Prerequisites=[0, 1], [1, 2], [2, 0]
Output: []
Explanation: The tasks have a cyclic dependency, therefore they cannot be scheduled.
Try it yourself
Try solving this question here:
Python3
Python3
. . . .
.....
.....
.....
Like the course? Get enrolled and start learning!
Table of Contents
Contents are not accessible
Contents are not accessible
Contents are not accessible
Contents are not accessible
Contents are not accessible