Estimating Effort and Risk
The seller tools team estimated 6 weeks to move seller sign-in to the company's new identity service. The work took 19 weeks. The team's code was not the problem: the tasks it had listed took about as long as planned. The 13 extra weeks came from work that was not on the list.
| Cause of the delay | Weeks added |
|---|---|
| The mobile app needed a new release, and sellers took weeks to install it | 5 |
| Shared seller accounts, where several staff use one login, had never been listed | 4 |
| The security review had a queue | 3 |
| One engineer spent a week on an unrelated incident | 1 |
.....
.....
.....