Problem Statement

There are ‘N’ tasks, labeled from ‘0’ to ‘N-1’. Each task can have some prerequisite tasks which need to be completed before it can be scheduled.

Given the number of tasks and a list of prerequisite pairs, find out if it is possible to schedule all the tasks.

Examples

Example 1:

Input: Tasks=6, Prerequisites=[2, 5], [0, 5], [0, 4], [1, 4], [3, 2], [1, 3]
Output: true
Explanation: A possible scheduling of tasks is: [0 1 4 3 2 5] 

Example 2:

Input: Tasks=3, Prerequisites=[0, 1], [1, 2]
Output: true
Explanation: To execute task '1', task '0' needs to finish first. Similarly, task '1' needs to finish before '2' can be scheduled. One possible scheduling of tasks is: [0, 1, 2] 

Example 3:

Input: Tasks=3, Prerequisites=[0, 1], [1, 2], [2, 0]
Output: false
Explanation: The tasks have a cyclic dependency, therefore they cannot be scheduled.

Try it yourself

Try solving this question here:

Python3
Python3

. . . .

.....

.....

.....

Like the course? Get enrolled and start learning!

Table of Contents

Contents are not accessible

Contents are not accessible

Contents are not accessible

Contents are not accessible

Contents are not accessible