A product sells 40 units a day. Its supplier promises delivery in 7 days, so a buyer reorders when stock falls to 40 x 7 = 280 units. Deliveries really take 11 days on average, so the shelf is empty for 4 days. The forecast was correct; the delivery time was wrong. A stock level that triggers a new order is called a reorder point, and with the real delivery time it should have been 40 x 11 = 440 units.
The Problem
The head of supply chain at a regional retailer describes the request:
"Our main warehouse stocks 18,000 products, and we keep running out of the ones people want. We als
.....
.....
.....